Best Practices Checklist: Confirming That the Critical Path Is Valid
The schedule’s critical path is valid. That is, the critical path or longest path (in the presence of constraints)
does not include LOE activities, summary activities, or other unusually long activities, except for future planning packages;
is a continuous path from the status date to the finish milestone;
does not include constraints that cause unimportant activities to drive a milestone date;
has no lags or leads;
is derived in summary schedules by vertical integration of lower-level detailed schedules, not by preselected activities that management has presupposed are important.
If backward-pass date constraints are present on activities other than the finish milestone, both the critical path and the longest path have been identified. With a number of constraints, activities with zero or negative total float may outnumber activities that are actually driving the key program completion milestone.
The critical path, or longest path (in the presence of constraints), is used as a tool for managing the program. That is, management has vetted and justified the current critical path as calculated by the software;
uses the critical path to focus on activities that will be detrimental to the key program milestones and deliveries if they slip;
examines and mitigates risk in activities on the critical path that can potentially delay key program deliveries and milestones;
has reviewed and analyzed near-critical paths because these activities are likely to overtake the existing critical path and drive the schedule;
recognizes not only activities with the lowest float but also activities that are truly driving the finish date of key milestones;
evaluates the critical path before the schedule is baselined and after every status update to ensure that it is valid.