Four Characteristics Of A Reliable Schedule
GAO’s research tells us that the four characteristics of a high-quality, reliable schedule are that it is comprehensive, well-constructed, credible, and controlled. A comprehensive schedule includes all activities for both the government and its contractors necessary to accomplish a program’s objectives as defined in the program’s WBS. The schedule includes the labor, materials, travel, facilities, equipment, and the like needed to do the work and depicts when those resources are needed and when they will be available. It realistically reflects how long each activity will take and allows for discrete progress measurement.
A schedule is well-constructed if all its activities are logically sequenced with the most straightforward logic possible. Unusual or complicated logic techniques are used judiciously and justified in the schedule documentation. The schedule’s critical path represents a true model of the activities that drive the program’s earliest completion date, and total float accurately depicts schedule flexibility.
A schedule is credible if it is horizontally traceable—that is, it reflects the order of events necessary to achieve aggregated products or outcomes. It is also vertically traceable: activities in varying levels of the schedule map to one another and key dates presented to management in periodic briefings are in sync with the schedule. Data about risks are used to predict a level of confidence in meeting the program’s completion date. Necessary schedule contingency and high-priority risks are identified by conducting a robust schedule risk analysis.
Finally, a schedule is controlled if trained schedulers update it regularly using actual progress and logic—based on information provided by activity owners—to realistically forecast dates for program activities. Updates to the schedule are accompanied by a schedule narrative that describes salient changes to the network. The current schedule is compared against a designated baseline schedule to measure, monitor, and report the program’s progress. The baseline schedule is accompanied by a basis document that explains the overall approach to the program, defines ground rules and assumptions, and describes the unique features of the schedule. The baseline schedule and current schedule are subjected to configuration management control. Table 7 shows how the 10 scheduling best practices can be mapped to these four characteristics.
Table 7: Best Practices Entailed in the Four Characteristics of a Reliable Schedule
Schedule characteristic | Best practice |
---|---|
Comprehensive, reflecting all
|
|
Well constructed, with
|
|
Credible, reflecting
|
|
Controlled, being
|
|