Best Practices Checklist: Maintaining a Baseline Schedule
A baseline schedule
- is set promptly after the program begins;
- is the basis for measuring performance;
- represents the original configuration of the program plan and signifies the consensus of all stakeholders regarding the required sequence of events, resource assignments, and acceptable dates for key deliverables;
- is compared to the current schedule to track variances from the plan.
The as-built version of the schedule is planned to be archived and will
- represent the plan as executed to completion;
- be compared to the original plan for an assessment of lessons learned;
- become a valuable basis of estimate input for schedule estimates of future analogous projects;
- become the basis for creating and validating fragnets where possible.
A schedule basis document is a single document that
- defines the organization of the IMS;
- describes the logic of the network;
- describes the basic approach to managing resources;
- provides a basis for all parameters used to calculate dates;
- describes the general approach to the project;
- defines how to use the schedule file;
- describes the schedule’s unique features;
- describes the schedule change management process;
- contains a dictionary of acronyms and custom fields;
- gives an overview of the assumptions and ground rules, including justification for
- calendars,
- lags,
- date constraints,
- long activity durations, and
- calendars and working times;
- describes the use and assignments of resources within the schedule in appropriate detail;
- describes the critical risks prioritized in a schedule risk analysis as well as schedule contingency;
- discusses the derivation of the critical paths, longest path, and total float for the program;
- is considered a living document that reflects updates to the baseline schedule.
Changes to the baseline schedule are reviewed and approved according to the change control process.
Schedule variances that exceed predetermined thresholds are reported to management, along with the cause and any corrective actions.
Negative schedule variances are investigated to see if the associated effort is on the critical path.
Schedule measures, such as the number of activities that have started or finished early, on time, or later than planned, are analyzed for the effect of any variances.
Trend analysis is conducted regularly to examine measures such as decreasing float and schedule contingency erosion.
The focus of any schedule recovery or acceleration techniques is on critical activities.