Best Practices Checklist: Maintaining a Baseline Schedule

  • A baseline schedule

    • is set promptly after the program begins;
    • is the basis for measuring performance;
    • represents the original configuration of the program plan and signifies the consensus of all stakeholders regarding the required sequence of events, resource assignments, and acceptable dates for key deliverables;
    • is compared to the current schedule to track variances from the plan.
  • The as-built version of the schedule is planned to be archived and will

    • represent the plan as executed to completion;
    • be compared to the original plan for an assessment of lessons learned;
    • become a valuable basis of estimate input for schedule estimates of future analogous projects;
    • become the basis for creating and validating fragnets where possible.
  • A schedule basis document is a single document that

    • defines the organization of the IMS;
    • describes the logic of the network;
    • describes the basic approach to managing resources;
    • provides a basis for all parameters used to calculate dates;
    • describes the general approach to the project;
    • defines how to use the schedule file;
    • describes the schedule’s unique features;
    • describes the schedule change management process;
    • contains a dictionary of acronyms and custom fields;
    • gives an overview of the assumptions and ground rules, including justification for
      • calendars,
      • lags,
      • date constraints,
      • long activity durations, and
      • calendars and working times;
    • describes the use and assignments of resources within the schedule in appropriate detail;
    • describes the critical risks prioritized in a schedule risk analysis as well as schedule contingency;
    • discusses the derivation of the critical paths, longest path, and total float for the program;
    • is considered a living document that reflects updates to the baseline schedule.
  • Changes to the baseline schedule are reviewed and approved according to the change control process.

  • Schedule variances that exceed predetermined thresholds are reported to management, along with the cause and any corrective actions.

  • Negative schedule variances are investigated to see if the associated effort is on the critical path.

  • Schedule measures, such as the number of activities that have started or finished early, on time, or later than planned, are analyzed for the effect of any variances.

  • Trend analysis is conducted regularly to examine measures such as decreasing float and schedule contingency erosion.

  • The focus of any schedule recovery or acceleration techniques is on critical activities.