Continue EVM until the Program is Complete

EVM detail planning continues until the program is complete. Rolling wave planning gives the contractor flexibility for planning the effort in detail and allows for incorporating lessons learned. Work may be planned by calendar dates, for example, in 6-month increments; all effort beyond 6 months is held in a planning package. Each month, near-term planning packages are converted to detailed work packages to ensure that 6 months of detailed planning are always available to management. This continues until all work has been planned in detail and the program is complete. However, rolling-wave planning based on calendar dates may result in insufficient detail. A best practice is to plan the rolling wave to a design review, test, or other major milestone rather than an arbitrary period, such as 6 months.

Continually planning the work supports an EVM system that will help management complete the program within the planned cost and proposed schedule. This is important because EVM data are essential to effective program management and can be used to answer basic program management questions such as those in table 25.

Table 25: Basic Program Management Questions That Earned Value Management (EVM) Data Help Answer
Scroll to the right to view full table.
Question Answer
How much progress has the program made so far?
  • Percent complete
What are the significant deviations from the plan?
  • Cost variance
  • Schedule variance
  • Variance at completion
How efficiently is the program meeting cost and schedule objectives? Cost performance index (CPI)
Schedule performance index (SPI)
Are cost and schedule trends getting better or worse? Plot cost and schedule variance, CPI, SPI, and the like
Will the program be completed within the budget? To complete performance index (TCPI) for the budget at completion (BAC)
Is the contractor’s estimate at completion (EAC) reasonable? TCPI for the contractor’s EAC
What other estimates are reasonable for completing the authorized scope of work? Independent EACs using statistical forecasting techniques based on various efficiency factors
What action will bring the program back on track? Acting on format 5 variance analysis information

Source: ICEAA (International Cost Estimating and Analysis). Cost Estimating Body of Knowledge. Vienna, Va.: 2013 | GAO-20-195G

From questions such as those in table 25, reliable EVM data can help inform the most basic program management needs. The questions also provide an objective way of measuring progress so that accurate independent assessments of EACs can be developed and presented to stakeholders.