When auditing a program that has conducted an IBR, there are several documents to review and questions to evaluate to determine if the IBR process was properly completed. The list of documents to be reviewed include
EVM contract performance reports (CPR), Formats 1-5, for the past 12 months
The most recent IBR report
IBR team training briefings and documentation
Any corrective action reports (CARs) generated by the IBR
The integrated master schedule (IMS) in its native software format
EVMS guidance or policy
Copy of EVM Certification to demonstrate EIA-748 compliance
Copy of any adverse opinions of the contractor’s financial accounting system
Copy of any EVM trends and metric analysis reports
Work Breakdown Structure (WBS) and WBS Dictionary
Statement of work
Work package descriptions
Risk plans
Staffing plans
Control account plans
Bases of estimates